FACILITIES MANAGEMENT

Lakeland Community College is undergoing a major construction project on campus to expand and renovate the Health Technologies Building and make other campus infrastructure improvements.

This construction is made possible thanks to: Lake County voter passage of the college's bond issue on Nov. 3, 2015; State of Ohio capital appropriations; and an Ohio Board of Regents Small Campus Targeted Workforce Expansion grant.

Construction Updates

Construction update #1(click link)

Construction update #2(click link)

Construction update #3(click link)

Live Webcam (updated 3-4 times / hour) - Click to view larger

 

Construction Plans
 
Construction Timeline
 
Spring 2016
  • Expansion of Health Building
     
Summer 2016
  • Expansion of Health Building continues
  • Renovation of H-101 lecture hall
     
Fall 2016 - Spring 2017
  • Expansion of Health Building continues
     
Summer 2017 - Fall 2017
  • Expansion of Health Building continues
  • Renovation of Health Building ground floors and connectors to C-Building
     
Fall 2017 - Spring 2018
  • Expansion of Health Building opens
  • Renovation of H-1095 lecture hall and H-Building first, second and third floors
     
Winter 2018
  • Renovation of EMS suite on H-Building second floor

 